NewsBauxiteNalco's bauxite mine renewal plan under Naxal threat
Business Standard

Nalco's bauxite mine renewal plan under Naxal threat

Edited by : AL CIRCLE
2 min read
Nalco's bauxite mine renewal plan under Naxal threat
Nalco, till date, has mined only one third of the deposit to meet its requirement in the last 30 years

The threat of Red rebels has cast a shadow of uncertainty over the renewal of National Aluminium Company's (Nalco) Panchpatmalli bauxite mines even as the company has intensified efforts to obtain Temporary Work Permit (TWP) for running the lease.

The boycotting of public hearing for renewal by the affected locals is believed to have thrown the company authorities into a tizzy who suspect Naxal hand behind the public not showing up. Forest clearance for the Panchpatmalli mine in Naxal infested Koraput district with deposits of around 300 million tonne is expiring on November 16.

Nalco, till date, has mined only one third of the deposit to meet its requirement in the last 30 years.

“ People are under the threat of the Naxalites. This explains why they are not turning up for the public hearing despite 45-day notice served by the district collector. The non-participation of the public is only going to make things tough for us as far as obtaining forest clearance is concerned. We feel our clearance may be delayed”, said a senior Nalco official.

Obtaining TWP, indispensable for running the mine under deemed extension also seems hard to come by. Some illegal constructions by Nalco within the mine lease area post Naxalite raid on the mines in April 2009 have apparently thrown a spanner in the works.

The state steel & mines department said it is ready to allow Nalco's mine to operate under deemed extension provided the company obtains TWP.

However, already suspecting delay in getting TWP, Nalco has prepared a contingency plan to build up bauxite stock of nearly 300,000 tonne, sufficient to run its alumina refinery for over a month in case the Panchpatmalli mining operation comes to a halt on November 16. It needs 260,000 tonne of bauxite a month for operating the refinery at full steam. Presently, Nalco is consuming 240,000 tonne of bauxite a month.

On Nalco’s bid to get hold of another bauxite mine at Patangi in Koraput district with 75 million tonne deposit, Rajesh Verma, secretary (steel & mines)-Odisha said, there are no issues for the state government recommending reservation of bauxite mine in favour of Nalco under Section 17 A-1A of the existing MMDR (Mines and Minerals- Development & Regulation) Act-1957.

Grow with
AL Circle

KNOW MORE

Responses

E-magazines

VIEW ALL
Aluminium extrusions

Turn marketplace visibility into more relevant buyer enquiries.

Boost Your Listing

Business Cards

FEATURED

VIEW ALL