Canyon Resources seeks A$70m as Minim Martap bauxite project faces major reset

Stock image for referential purposes only
Canyon Resources has launched a AUD 70 million (USD 46.42 million) entitlement offer to advance its Minim Martap Bauxite Project in Cameroon, while withdrawing the project’s Definitive Feasibility Study (DFS) outcomes, Ore Reserves, production targets and financial forecasts, post a review of its development plans.
The company now expects its first bauxite shipment in June 2027, subject to funding and the completion of key logistical arrangements.
The renounceable entitlement offer is priced at AUD 0.034 (USD 0.023) per share, with eligible shareholders entitled to subscribe for one new share for every existing share held. Canyon expects to raise up to AUD 70 million (USD 46.42 million) before costs, though the current shortfall stands around AUD 48 million (USD 31.83 million).
Explore: Most comprehensive and forward-looking industry-focused report — Global Bauxite & Alumina Market Forecast to 2036: Supply–Demand, Trade Flows & Price Outlook
The financing pause has affected the company’s development schedule, prompting it to withdraw its target of making the first bauxite shipment in the fourth quarter of 2026, along with a voluntary trading halt in its securities on the Australian Securities Exchange.
The proceeds are intended to fund the remaining project development activities and initial working capital requirements through to the first shipment. However, as the offer would not cover the proposed Stage 2 expansion or debt servicing obligations to AFG, additional funding is a requisite.
The revised project outlook follows delays in securing funding for planned rail infrastructure upgrades and additional rolling stock. With no sufficient capital expenditure expected during the remainder of 2026 or in 2027, Canyon anticipates relying substantially on the existing rail fleet for at least the next three years.
The current fleet has an estimated transportation capacity of around 35,000 tonnes per month, placing a constraint on the project’s near-term production potential. The procurement of additional rolling stock could also take 14 to 18 months.
In light of these limitations, Canyon has adopted a more gradual development and production ramp-up strategy and is no longer providing production volume forecasts. While the company has withdrawn its DFS outcomes, Ore Reserves and associated production and financial projections, its Mineral Resource estimates remain unchanged. Canyon has also stated that the material assumptions underpinning those estimates continue to be considered valid by the company and its Competent Person.
The first bauxite shipment is now targeted for June 2027, replacing the earlier Q4 2026 timeline. This remains conditional on sufficient subscriptions to the entitlement offer and the completion of outstanding arrangements, including transhipping and port dredging.
The revised schedule and funding requirements throw light on the importance of securing capital and resolving transportation constraints before the Minim Martap bauxite project can progress towards its first shipment.