Altech Chemicals Limited has provided an update on the current status of Stage 1 construction activities at its high purity alumina (HPA) plant site in Johor, Malaysia. Stage one construction work is progressing as planned.

They have finished erection of the steel structure for the maintenance workshop frame and roof. The cladding of the roof and canopy is also complete. Altech updates that the installation of internal mezzanine flooring and cladding of the building walls is currently going on. About 90% of work is finished on the wall construction along both the western and eastern site boundaries. The internal site retaining wall construction is complete and the area is currently undergoing backfilling.
Construction is going on for the on-site detention (OSD) storm water tanks according to the plans. They have completed the pouring of the base concrete floors for all four tank zones. Wall casting work for the first three tanks has started. Installing of the concrete roof panels will complete the OSD tank construction.