Metro Mining completes $3.6M entitlement issue

In July the company raised 2 million through the placement of 25 million shares at 0.08. Besides completing the DFS proceeds will also be used for:
- Complete authorities and licenses to operate the Bauxite Hills Project (environment approvals Native Title Agreements);
- Secure pre-commitments for mining and transhipment contractors as required; - Exploration activities and business development;
- Proposed buy-back of shareholders’ un-marketable parcels; and
- Provide working capital.
Bauxite Offtake
In August the company signed an offtake agreement with Xinfa Group - one of the largest integrated aluminium companies in China.
The non-binding offtake agreement contemplates a minimum contract tonnage of 1 million tonnes of bauxite a year up to a maximum of 1.2 million tonnes a year over the initial five years term – representing around half of the annual production.
Bauxite Hills has an Ore Reserve of 48.2 million tonnes with high grade total alumina of 50.2% and reactive silica of 6.3%. It is on track for first production in the third quarter of 2016.
Unlock full access – sign up for FREE.
Key benefits
Odisha Mining Corporation to fast track bauxite mining to rescue Vedanta refinery
Next articleVedanta urges Odisha government to secure bauxite for refinery survival
Grow with
AL Circle