Alcoa funds $20 million substation overhaul

The modernised McKenzie and Valhalla substations are owned respectively by Chelan County Public Utility District (PUD) and the Portland (Oregon)-based Bonneville Power Administration (BPA).
However, the Chelan County PUD has used part of the funding it received from Alcoa to buy a share in the Valhalla substation, making it the primary electricity supplier for the Wenatchee smelter.
Chelan PUD manager George Velazquez told the Wenatachee World website that both substations were now working and that they had to remain active throughout the overhaul process in order to maintain a power supply to the smelter's potlines.
During the overhaul – which brought together Chelan PUD, Alcoa and BPA – some of the parts replaced at both substations were over 60 years old.
Citic Resources says no to aluminium smelter purchase
Next articleAluminum smelter offers Japanese buyers 6.3% increase in the premium: sources
Grow with
AL Circle