Idle since 2020, Rio Tinto’s Tiwai Point aluminium smelter Line 4 eyes 2027 comeback

This image has been sourced from https://www.riotinto.com/en/news/multimedia-gallery
Rio Tinto is set to expand its aluminium production in New Zealand. The company has secured a three-and-a-half-year electricity agreement with Contact Energy to restart Line 4 at its Tiwai Point aluminium smelter. Backed predominantly by renewable energy, the 50MW power supply contract is expected to restore around 30,000 tonnes of annual aluminium production, taking the smelter’s capacity back to approximately 360,000 tonnes per annum (TPA).
The production boost would also reinforce Rio Tinto’s aluminium production across Australia and New Zealand, adding around 3 per cent to its regional smelting capacity. At current global spot aluminium prices, the increased production could generate around NZD 100 million (USD) in additional annual export revenue for New Zealand.
Explore the production, demand and consumption forecasts of bauxite and alumina in our report: "Global Bauxite & Alumina Market Forecast to 2036: Supply–Demand, Trade Flows & Price Outlook"
Renewable power paves the way for Line 4 restart
The new agreement is based on a Letter of Intent signed by Rio Tinto and Contact Energy, announced earlier this year, under which the two fronts began discussions on a sustainable and affordable arrangement to bring the idle potline back online.
Armando Torres, Managing Director of Rio Tinto Aluminium Pacific Operations, stated, “The restart of Line 4 will increase aluminium production at a time when demand for high-quality, low-carbon aluminium has never been higher.” The agreement bolsters Rio Tinto’s commitment to its New Zealand base, which is an essential part of the company’s “integrated aluminium operations globally.”
Explore primary aluminium suppliers, product listings and trade opportunities on the AL Biz platform.
Production revival targeted for late 2027
The Line 4 restart is scheduled to begin in October 2027, following operational preparations and commissioning, with full production expected by December 2027. The electricity agreement is to initially supply 50MW, reducing to 25MW during winter to avoid any additional pressure on New Zealand’s wider energy security.
Rio Tinto New Zealand Aluminium Smelters General Manager Michelle Henderson noted that the electricity contract would pave the way for “an early restart of Line 4” while a “longer-term power purchase agreement that could see Line 4 operate for the next two decades at least” remains in the making.
“This is great news for the Southland and wider New Zealand economies,” Henderson added.
Line 4 at Tiwai Point has remained idle since April 2020, owing to the COVID-19 pandemic-led disruptions and the subsequent uncertainty surrounding the aluminium smelter’s long-term future. Rio Tinto has since secured long-term electricity supply arrangements extending into the coming decades, ensuring a stronger foundation for the production reboot.
The Line 4 revival marks another cornerstone in the company’s project ledger after Rio Tinto’s Weipa operations expansion, announced last week, which entailed a USD 2.6 billion Kangwinan bauxite project in Queensland, expected to add 20 million tonnes of annual bauxite production capacity, with first output targeted for 2029 and full production anticipated by 2032.