Nalco to set up wind power project in Jaisalmer
The move is part of the diversification plans of National Aluminium Company Limited (Nalco), a navratna PSU, which has been foraying into other metals and energy sectors. This is the company's second green initiative towards promoting sustainable development by harnessing the unconventional and renewable energy sources. The move is also likely to credit the company with incentives from the government.
N R Mohanty, director (P&T), Nalco, laid the foundation-stone of the project on January 12, in presence of S K Dash, executive director (P&T). Earlier, the company commissioned its first wind power plant of 50.4 MW capacity at Gandikota in Kadapa district of Andhra Pradesh, on December 30, 2012.
As part of the project, 24 wind turbines, each of 2.1 MW rating, were erected, at an investment of Rs 274 crore with Suzlon Energy Limited as the executing agency.