NewsBauxiteMetro Mining provides further construction update for Bauxite Hills Mine
01 SEPTEMBER 2017AlCircle.com

Metro Mining provides further construction update for Bauxite Hills Mine

Edited by : Heena Iqbal
1 min read
Metro Mining provides further construction update for Bauxite Hills Mine

Metro Mining Limited yesterday provides a construction update for the Bauxite Hills Mine. The construction work at the site is currently on schedule, and will be completed by the end of 2017.

Barge Loading Facility (BLF) fabrication commences in Cairns by CSF Steel Fabricators. The shipment to site is planned for mid-September.  Foreshore Marine has installed the tidal gauge and cyclone moorings in the Skardon River.


 “Mining equipment has arrived on site with civil works commencing immediately to clear the Port and approved Barge Loading Facility (BLF) areas. Additional civil works including upgrading the existing roads and sediment dam works are also in progress,” the company said.


Metro’s Site Environmental Officer has arrived on the Mine site and will supervise construction activities, commence operations readiness preparation. The company has signed a deal with Falck for the provision of a paramedic and medical supplies at Bauxite Hills.

The company announced that the Minister for State Development, Natural Resources and Mines Hon Dr Anthony Lynham grants the three mining leases for the Bauxite Hills Mine.

Grow with
AL Circle

KNOW MORE

Responses

E-magazines

VIEW ALL
Aluminium extrusions

Turn marketplace visibility into more relevant buyer enquiries.

Boost Your Listing

Business Cards

FEATURED

VIEW ALL