Nalco commissions INR 283 crore wind power project in Jaisalmer

The INR 283-crore wind power project is being executed through Gamesa Wind Turbines Private Ltd.,which involves erection of 56 Wind Turbines, each of 850 KW rating. This is Nalco's second green initiative towards promoting sustainable development by harnessing the unconventional and renewable energy sources, which would credit the company with incentives from the government. The project is scheduled to be completed by August 2013.
Earlier, the company commissioned its first Wind Power Plant of 50.4 MW capacity at a cost of INR 274 crore at Gandikota in Kadapa district of Andhra Pradesh, in December, 2012. It is also planning to set up the third wind power plant in its own mined out area of Panchpatmali bauxite deposit in Odisha's Koraput.