Metro Mining provides construction update for Bauxite Hills project

Metro Mining Media Release

Metro Mining Limited is pleased to provide a construction update for the Bauxite Hills project, which is now fully funded through to the commencement of production.

 SAB Mining has been mobilised to site to commence civil works. SAB’s initial focus will be at the Port area, preparing the site for marine infrastructure. After this, SAB will then commence upgrades of the existing roads, and construction of new haul roads.

{alcircleadd}

news

The fabrication of the BLF jetty piles and structural steel has been completed in China and is currently being shipped to Australia. The tug and barge fleet provided by Transhipment Services Australia (TSA) has being mobilised and on route to site will pick up piles, steel and other equipment. A separate barge will be set up for marine piling works.

Once at site, the jetty piles and steel headstocks will be installed in the Skardon River by Foreshore Marine QLD. Concurrently, the Barge Loading Facility conveyor system is being designed and managed by Process 26 and fabricated in Cairns by CSF Steel Fabricators. Once complete it will be shipped to site for installation.

Construction of the Bauxite Hills accommodation village is also progressing well. Twelve bunk-houses have already completed and will be mobilised to site early to provide additional accommodation during construction.

{googleAdsense}

The port area has been cleared and ready for construction of the Barge Loading Facility. Much of the on-site infrastructure has been incorporated into the project design including utilising existing buildings for the laboratory, warehouse, maintenance facilities, and offices. Existing tanks will be used for water storage.

Metro is also focussed on providing employment opportunities through the company and its contractors for the traditional owners of the land, the Ankamuthi people, and the greater indigenous community. Based on current personnel on site, Metro has achieved Indigenous employment of 25%.

Metro’s Managing Director, Simon Finnis, said: “This is an exciting time for Metro and our shareholders. The company has entered the execution phase and we are committed to delivering the Bauxite Hills mine on time and on budget. 

Edited By:


This news is also available on our App 'AlCircle News' Android | iOS


Alternate Text
EPIQ Machinery

A world class equipment designer specialized in developing innovative & effective solutions for heavy equipment, vehicles, and material handling systems

Alternate Text
RIA Cast House Engineering

Leading supplier of rail mounted precision Furnace Charging Machines and Furnace Skimming Machines

Alternate Text
Altek

Leading manufacturer of value-added equipment for the aluminum casthouse

Alternate Text
Jagannath Company

Manufacturers & Supplier of Magnesium Metal and Aluminium Foundry Chemicals

Alternate Text
CETAG

A supplier of proven systems and an expert adviser in aluminum casthouse technology, offering its services worldwide to the aluminum industry.

Alternate Text
IBAAS​-IIM 2024

September 25-27, 2024 | BITS Pilani K K Birla Goa Campus, Goa, INDIA

Related
Business Leads
We need bauxite in bulk quantity and is looking for supplier...
02-Apr-2024 Buying request

Interested to buy bauxite ore. Total Quantity: As per buyer...
19-Jan-2024 Buying request

Interested to buy bauxite. Please share prices for highest,...
16-Dec-2023 Buying request

Read this news article and much
more on the AL News app
Get real-time news and business
lead alerts on your phone
SUBSCRIBE NOW
Market

Market

Project

Project

Technology

Technology

Leads

Leads